Border Development Projects
Santa Teresa, NM
New Mexico Border Authority
January 21, 2015
On-Going State or State Sponsored Development Projects at Santa Teresa |
Project |
Status |
Total Estimated Funding Requirement |
State Funding |
Federal Funding Or Private |
Estimated Additional Funding Required or Pending |
Estimated Completion
|
Anapra POE |
Pre-Presidential Permitting: Environmental Assessment |
$1.5 million (Presidential Permit) |
$12.0 million (City of Sunland Park funds) |
|
TBD |
TBD |
Commercial Safety Inspection Facility |
Design |
$14 million +/- |
$3.4 million |
$7.6 million |
$3 million +/- |
Feb 2015 |
NMBA Office Building |
Construction Completed |
$1.4 million |
$1.4 million |
|
|
May 2010 |
POE Commercial Hours Extension: 8:00 am-8:00 pm |
Permanent Extension Authorized March 2008 |
n/a |
|
|
|
Authorized |
POE Additional Passenger Vehicle Lanes |
GSA |
$11 million |
---- |
$11 million |
$3 million |
Completed August 12, 2012 |
POE Visitor Parking and New Import Lane |
Final Design |
$ 1 million |
$.250 million |
$.750 million |
|
Completed |
POE Export Lane Lighting |
Completed April 2008 |
$50,000 |
$50,000 (federal pass- through) |
|
|
Completed |
UPRR Relocation and Expansion |
Property Acquired |
$400 million |
0 |
0 |
NA |
Completed April 2014 |
Strauss Road – UPRR Intermodal Access |
Capital Outlay Awarded (2007) |
TBD |
$1.5 million |
$14 million |
|
Completed |
Rail Interconnection with Mexico BNSF/UPRR/FXE HNTB Study |
Pre- Presidential Permitting |
$1.2 million |
---- |
$1.2 million |
$556,000 Match |
July 2015 |
HAZMAT/Fire Emergency Response Facility |
NMBA Project |
$3.8 million |
$.375 million ( plus land donation by Verde Gp). |
$1.2 million |
$2.2 million |
Completed |
Dual Customs Pilot Project |
Approved NMBA |
$400,000 |
$400,000 Capital Outlay |
---- |
$700,000 |
Construction In Progress DAC |